Part 2: The procurement took longer than planned
>
But the procurement took longer and was more costly than planned
But the procurement took longer and was more costly than planned
More Information
The procurement timetable was extended on six occasions
The procurement took longer than other ground-breaking Private Finance projects
The Contributions Agency's procurement costs increased
Bidders were concerned about the costs they incurred
There were several reasons why the procurement took longer than expected
The Department's requirements developed after the Contributions Agency began formal procurement
Inter-agency co-operation within the Department proved difficult
Important issues remained to be settled when the Department appointed a preferred supplier
The Contributions Agency continued negotiations until satisfied with the deal
NEP took five months to conclude its external funding arrangements