Advisers were appointed in good time and costs were controlled

3.4  National Savings appointed advisers in good time following competitions in which success depended on the quality of advice on offer, having regard to price. Budgets were prepared to monitor advisers' fees against actual costs (Figure 11). The overall budget for both the original accommodation project and the partnership to run the operational service was exceeded by 14 per cent. This included unplanned expenditure on the accommodation project of £253,000. The scope of the accommodation project was extended beyond initial expectations and took longer than expected to define. This resulted in the need for a greater level of professional advice. When extra spending was proposed, however, National Savings' project board and finance directorate scrutinised the proposals and authorised further spending so that budgets were never exceeded without authority.

 

Cost of National Savings advisers

Figure 11

 

 

 

This figure shows that National Savings exceeded its budget by 14 per cent

 

Adviser

Budget £000s

Actual £000s

Variations £000s

 

Operational Services

 

 

 

 

PA Consulting

1,519

1,609

90

 

Herbert Smith

722

902

180

 

Dresdner Kleinwort Benson

325

280

(45)

 

Other

139

102

(37)

 

Total

2,705

2,893

188

 

Accommodation

 

 

 

 

Herbert Smith

 

200

 

 

Richard Ellis

 

187

 

 

Dresdner Kleinwort Benson

 

109

 

 

Other

 

105

 

 

Total

348

601

253

 

Overall Total

3,053

3,494

441

 

 

Notes:

1. These figures exclude VAT.

2.  Other operational services advisers: Corporate Value Associates; Arthur Andersen; Central Computer and Telecommunications Agency and Government Actuary's Department.

3.  Other accommodation advisers: Edmund Kirby; PACE and Burness.

4.  Expenditure shown under accommodation represents 86 per cent of the cost of advisers for the separate accommodation deal before it was incorporated into the main operational services PFI deal.

Source: National Savings