This Appendix provides information about the sample of twelve information technology projects included in the examination.
Project Name and description |
| ||||
| Estimated EDS lifecycle cost (£m) | Estimated total lifecycle cost (£m) | Status during Lorien fieldwork | ||
Computerised environment for self assessment (CESA) - Release 2 | |||||
This was the second stage of the information technology project designed to support the implementation of the income tax self assessment initiative and related to the development of software to enable taxpayer returns to be entered and processed. Separate costs were not available for this element of the project. | |||||
| N/A | N/A | Completed | ||
Infrastructure 2000 | |||||
Department-wide programme to upgrade desktop IT systems. | |||||
| 122 | 203 | In development | ||
Construction industry scheme | |||||
Development of new system to support reform of tax collection in the construction industry. | |||||
| 55 | 102 | In development | ||
Collection of student loan repayments | |||||
To enable the Department to assume responsibility for the collection of student loan repayments, and to pay over and pass details of payments to the Student Loans Company. | |||||
| 8 | 32 | In development | ||
Payroll and personnel management information system | |||||
To develop an integrated payroll and personnel management information system. | |||||
| 8 | 28 | Completed | ||
Individual savings accounts | |||||
To support introduction of individual savings accounts from April 1999. | |||||
| 9 | 21 | In development | ||
Integrated debt management system | |||||
To develop a fully integrated debt management environment. | |||||
| 1 | 16 | In development | ||
Call centre experiment | |||||
To set up a fully functional executive call centre to assess the viability of a national call centre network. | |||||
| 2 | 13 | In development | ||
Business continuity implementation | |||||
To provide a disaster recovery facility for critical mainframe services. | |||||
| 2 | 12 | Completed | ||
Integrated repayments system | |||||
To develop an integrated repayments system for the Financial Intermediaries and Claims Office. | |||||
| N/A | 4 | Completed | ||
Repayment of interest on PAYE | |||||
Enhancement to BROCS system (Business Review of the Collection Service) to introduce a cost-effective and efficient means of repaying interest in cases of PAYE overpayments. | |||||
| 0.6 | 0.7 | Completed | ||
Regional processing centre rationalisation | |||||
EDS performance improvement programme involving the closure of three regional processing centres. | |||||
| N/A | N/A | Completed | ||