Key Dates in the Procurement Timetable

The Project Team has developed a detailed project management plan and procurement timetable.  The procurement timetable has been agreed with Members and was included in the Outline Business Case for the project.  Key dates from the timetable are shown in the table below:

Stage

Actual or Planned Date

OJEU Notice Published

 

Descriptive Document and Pre-Qualification Questionnaire issued

 

Bidders Open Day

 

Return of PQQ

 

List of Pre-Qualified Bidders determined

 

Competitive Dialogue opened and outline solutions invited

 

Submission of Outline Solutions (ISOS)

 

Short-List for Competitive Dialogue on Detailed Solutions selected

 

Invitation to Submit Detailed Solutions issued (ISDS)

 

Date for Return of Detailed Solutions

 

Close of Competitive Dialogue and Final Tenders sought

 

Preferred Bidder selected

 

Contract Award