16.1  Notice

If at any time the Contractor becomes aware that there will be or is likely to be a delay in the [Initial Refurbishment] Works such that a [Start on Site Date]  [Planned Refurbishment Completion Date] [Planned Services Commencement Date] may not be achieved, the Contractor shall as soon as reasonably practicable and in any event within [twenty [20] Business Days of becoming aware of the likely delay give notice to the Authority to that effect specifying:

16.1.1  the reason for the delay or likely delay; and

16.1.2  an estimate of the likely effect of the delay on the [Initial Refurbishment] Works including the [Start on Site Date] [Planned Refurbishment Completion Date]  [Planned Services Commencement Date] (taking into account any measures that the Contractor proposes to adopt to mitigate the consequences of the delay in accordance with clause 16.3 (Duty to Mitigate)).