20.5  Site Clearance

The Contractor shall, as soon as is reasonably practicable following issue of an Certificate of Availability for a Dwelling, clear from the relevant Site, Dwelling and Property to the reasonable satisfaction of the Authority all temporary structures, rubbish and all building and surplus material and equipment and in default the Authority shall be entitled to employ an alternative contractor to clear them and shall be entitled to be reimbursed by the Contractor for any costs reasonably incurred in clearing or procuring the clearing of them provided that the Authority shall not be entitled to exercise such right for a period of five (5) Business Days following the date of the Certificate of Availability for that Dwelling.