32.5  Copies of licensed materials to be made available to the Authority

Within twenty (20) Business Days of the receipt by the Contractor of a written request from the Authority, the Contractor shall (insofar as permitted by Legislation, including without limitation the Data Protection Act 1998) promptly deliver to the Authority or to any third party on its behalf all or any data, materials, know how and/or information licensed under clause 32.3 (Licences and Assignments from the Contractor to the Authority)  and/or which is relevant for the maintenance, management, provision, replacement, carrying out and operation of the Works and/or Services in the Contractor's possession, custody or control or sub-contractor and any consultant (and/or, in each case, any subcontractor of the same) in each case at the date of such request, subject to the Authority paying the Contractor's reasonable copying fees.  Upon cessation of such licence for whatever reason, the Authority shall forthwith return all such materials so supplied (and any copies made thereof).