51.1 Occurrence
If and to the extent that a Relief Event:
51.1.1 is the direct cause of a delay to a [Planned Refurbishment Completion Date] [Planned Services Commencement Date]; and/or
51.1.2 adversely affects the ability of the Contractor to perform any of its obligations under this Agreement,
then the Contractor shall be entitled to apply for relief from any rights of the Authority arising under clause 37.4 (Termination on Contractor Default) [and its obligations under this Agreement]253
__________________________________________________________________________________________
253 In most contracts Relief Events should give only relief from the risk of termination for failure to complete or failure to perform. In cases in which liquidated damages are payable to the Authority there will be an issue of the extent to which relief can be given from claims for damages or liquidated damages. The performance regime should still apply and this should be made clear, to the extent there is potential for relief from liquidated and other damages.