54.2  Notice to the Contractor

If clause 54.1 (Right to Step-In) applies and the Authority wishes to take action, the Authority shall notify the Contractor in writing of the following:

54.2.1  the action it wishes to take;

54.2.2  the reason for such action;

54.2.3  the date it wishes to commence such action;

54.2.4  the time period which it believes will be necessary for such action; and

54.2.5  to the extent practicable, the effect on the Contractor and its obligation to [carry out the Works and/or] provide the Services during the period such action is being taken.