57.1  Requirement to Maintain

57.1.1  The Contractor shall prior to the Services Commencement Date, take out and maintain or procure the maintenance of the insurances described in Part 1 of Schedule 11 (Insurances) and any other insurances as may be required by law.  These insurances must be effective in each case not later than the date on which the relevant risk commences278.

57.1.2  The Contractor shall during the Services Period take out and maintain or procure the maintenance of the insurances described in Part 2 of Schedule 11 (Insurances) and any other insurances required by law. These insurances must be effective in each case not later than the date on which the relevant risk commences




__________________________________________________________________________________________

278  These are the construction or development phase insurances and must be required insurances only.  The insurance schedule should specify the dates by which these insurances should be effective.