57.7  Breach

If the Contractor is in breach of clauses 57.1.1 and 57.1.2 (Requirement to Maintain) above, the Authority may pay any premiums required to keep such insurance in force or itself procure such insurance and may, in either case, recover such amounts from the Contractor on written demand281.




__________________________________________________________________________________________

281  These amounts can be set off under clause 33.8 (Rights of Set Off).