60.17  Similar Disputes

If any dispute arising under this Agreement raises issues which relate to:

60.17.1  any dispute between the Contractor and the [Building] [Refurbishment] Contractor arising under the [Building] [Refurbishment] Contract or otherwise affects the relationship or rights of the Contractor and/or the [Building] [Refurbishment] Contractor under the [Building] [Refurbishment] Contract (the [Building] [Refurbishment] Contract Dispute); or

60.17.2  any dispute between the Contractor and the Housing Management Contractor arising under the Housing Management Agreement or otherwise affects the relationship or rights of the Contractor and/or the Housing Management Contractor under the Housing Management Agreement (the Housing Management Agreement Dispute),

60.17.3  any dispute between the Contractor and the Responsive Repairs and Cyclical Maintenance and Renewal Contractor arising under the Responsive Repairs and Cyclical Maintenance and Renewal Contract or otherwise affects the relationship or the right of the Contractor and/or Responsive Repairs and Cyclical Maintenance and Renewal Contractor under the Responsive Repairs and Cyclical Maintenance and Renewal Contract (the Responsive Repairs and Cyclical Maintenance and Renewal Contract Dispute).

then the Contractor may include as part of its submissions made to the Adjudicator or to the Arbitrator, where the dispute is referred to arbitration, submissions made by the [Building] [Refurbishment] Contractor, or by the Housing Management Contractor or Responsive Repairs and Cyclical Maintenance and Renewal Contractor as appropriate.