17.  Testing and Sampling

17.1  The Contractor shall carry out all on-site performance tests and sampling as are reasonably necessary in accordance with Good Industry Practice.

17.2  All architectural components, plumbing, gas and electrical installations shall meet all requirements of such tests as defined in the relevant British Standard Codes of Practice.

17.3  All Tenants are to be provided with all relevant manufacturers instructions (if any) for items installed.  In addition operating instructions must be communicated to the Tenant in such a manner that the Tenant can readily understand them.