6.5  Authority Warranted Data161



The Authority warrants to the Contractor that the Housing Information set out or described in Part 1 of Schedule 9 (Warranted Data) has been prepared after due and careful enquiry and is in all materials respects true, accurate and complete as at the date of this Agreement.




__________________________________________________________________________________________

161 Generally only relevant to HRA refurbishment projects. This clause should not be used if the only data in Schedule 9 (Warranted Data) is employee information. No warranty is to be given in respect of employee information because the cost adjustment mechanism is being used  - see clause 29.4.1 (Authority Warranted Data) and footnote below.