20.2 Issue of Certificate of Availability
20.2.1 The Authority and the Contractor shall procure that the Independent Certifier certifies Dwellings which have achieved the relevant Availability Standards on the [30th] of each Month.
20.2.2 The Authority and the Contractor shall procure that where the Independent Certifier considers that the relevant Availability Standards have been satisfied, [and that all outstanding [Initial Refurbishment] Works detailed in the Snagging List can be carried out within [20] Business Days of the issue of the Certificate of Availability] the Independent Certifier will issue a Certificate of Availability with copies to the Authority and the Contractor.