47.1 Delivery of Initial and Changed Project Documents and Financing Agreements
47.1.1 The Contractor has provided to the Authority copies of the Project Documents [(as listed in Schedule 14 (Project Documents))] and of the Initial Financing Agreements [(as listed in Parts 1 and 2 of Schedule 13 (Financing Agreements))].
47.1.2 Without prejudice to the provisions of clauses 47.2 (Changes to Project Documents) or 47.3 (Changes to Financing Agreements), or to the definition of Senior Financing Agreements in clause 1.1 (Definitions), if at any time an amendment is made to any Project Document or Financing Agreement, or the Contractor enters into a new Project Document or Financing Agreement (or any agreement which affects the interpretation or application of any Project Document or Financing Agreement), the Contractor shall deliver to the Authority a conformed copy of each such amendment or agreement within ten (10) Business Days of the date of its execution or creation (as the case may be), certified as a true copy by an officer of the Contractor.