52.4 Funding for Capital Expenditure
If the parties agree or it is determined under the Dispute Resolution Procedure that the Contractor is required to incur additional Capital Expenditure due to a Qualifying Change in Law (excluding the Contractor's Share of any Capital Expenditure agreed or determined to be required as a result of a General Change in Law under this clause 52.4), then the Contractor shall use its reasonable endeavours to obtain funding for such Capital Expenditure on terms reasonably satisfactory to it and to the Senior Lenders.