58A.4  Contractor Breach

If, pursuant to clause 58A.3 above, insurance proceeds are released from the Joint Insurance Account the Contractor shall be in breach of its obligations under this Agreement, and shall not, pursuant to clause 51 (Relief Events), be relieved of its obligations unless it can demonstrate, to the satisfaction of the Authority, that it can carry out the works necessary to repair, reinstate or replace the assets which are subject to the relevant claims in accordance with clause 58.4 (Reinstatement and Change of Requirement after Insured Event) and within a reasonable timescale.