2. Further Information
2.1 The Contractor shall submit any further or other information, data and documents that the Authority's Representative reasonably requires in order to determine whether he has a basis for raising comments or making objections to any Submitted Item in accordance with paragraph 3 (Objections). If the Contractor does not submit any such information, data and documents, the Authority's Representative shall be entitled to:-
2.1.1 raise comments or make objections on the Submitted Item in accordance with paragraph 3 (Objections) on the basis of the information, data and documents which have been provided; or
2.1.2 make objections to the Submitted Item on the grounds that insufficient information, data and documents have been provided to enable the Authority's Representative to determine whether he has a legitimate basis for commenting or objecting in accordance with paragraph 3 (Objections).