4. Authority Report
4.1 An Authority Report will be issued each month to the Authority by the Contractor. The report will provide details, inter alia, of the following:
4.1.1 a statement of progress as against any Programme of [Initial Refurbishment] Works;
4.1.2 status of all consents and approvals;
4.1.3 resume of the reasons for any delay;
4.1.4 actions to be taken to mitigate delays;
4.1.5 Works Changes requested by the Contractor and approved;
4.1.6 impact of any Works Change requested by the Authority including any possible adjustment of the Unitary Charge;
4.1.7 a statement as to current design development;
4.1.8 outstanding information required from the Contractor;
4.1.9 health and safety issues; and
4.2 Where it is agreed that there is a material or significant change in any Programme of [Initial Refurbishment] Works then the Contractor will issue to the Authority all such revisions of the Programme of [Initial Refurbishment] Works within five (5) Business Days.
4.3 This paragraph does not apply to Responsive Repairs.