Appendix 1 - Catalogue of Low Value Change

The parties shall agree an all-inclusive unit price (for purchase and installation), and standard timescales (wherever practicable) for implementation of Low Value Changes and other changes which do not affect the risk profile of the Project (unit prices should be selected from Appendix 2 Part 1 where they meet the criteria of a Low Value Change).

The Catalogue should also contain a schedule of rates for any specialist services that may be required by the Contractor to process any Low Value Changes.  A typical list of specialist services is provided below.