Risk Quantification
Ref | Risk category | Risk definition | Risk allocation for PFI option | Initial high level assessment (High [H], Medium [M] or Low [L]) | Detailed quantification of high and medium risks | |||||||||
Cost impact £'000s | ||||||||||||||
LA | SP | Share | Probabilty of occurrence (H/M/L) | Cost impact (H/M/L) | Overall significance (H/M/L) | Probability of occurrence % | Timing | Cost Base | Minimum | Most likely | Maximum | |||
1 | Develop | Business Case |
|
|
|
|
|
|
|
|
|
| ||
2 | Develop | Compliance with Best Value Review (pre Contract Award) |
|
|
|
|
|
|
|
|
|
| ||
3 | Develop |
|
|
|
|
|
|
|
|
|
| |||
4 | Develop |
|
|
|
|
|
|
|
|
|
| |||
5 | Develop | Data Room |
|
|
|
|
|
|
|
|
|
| ||
6 | Develop | Development Costs |
|
|
|
|
|
|
|
|
|
| ||
7 | Develop | DfT Approval and Funding in place |
|
|
|
|
|
|
|
|
|
| ||
8 | Develop | Economic Case (AST) |
|
|
|
|
|
|
|
|
|
| ||
9 | Develop | Execution and Delivery of Documents |
|
|
|
|
|
|
|
|
|
| ||
10 | Develop | Licences |
|
|
|
|
|
|
|
|
|
| ||
11 | Develop | Local Authority Agreements in Place |
|
|
|
|
|
|
|
|
|
| ||
12 | Develop | Local Authority Approval and Funding in place |
|
|
|
|
|
|
|
|
|
| ||
13 | Develop | PRG Approvals in place |
|
|
|
|
|
|
|
|
|
| ||
14 | Develop | Procurement Costs |
|
|
|
|
|
|
|
|
|
| ||
15 | Develop | Project Affordability |
|
|
|
|
|
|
|
|
|
| ||
16 | Develop | Project Specification |
|
|
|
|
|
|
|
|
|
| ||
17 | Develop | Stakeholder Consultation - Members/Users/Others |
|
|
|
|
|
|
|
|
|
| ||
18 | Develop | Value for Money Assessment |
|
|
|
|
|
|
|
|
|
| ||
19 | Develop | Vires |
|
|
|
|
|
|
|
|
|
| ||
20 | Design | Access Agreements and Consents |
|
|
|
|
|
|
|
|
|
| ||
21 | Design | Changes in Design Standards & Codes of Practice |
|
|
|
|
|
|
|
|
|
| ||
22 | Design | Changes in design due to influences external to the Local Authority & Service Provider |
|
|
|
|
|
|
|
|
|
| ||
23 | Design | Changes requested by Service Provider |
|
|
|
|
|
|
|
|
|
| ||
24 | Design | Changes requested by Local Authority |
|
|
|
|
|
|
|
|
|
| ||
25 | Design | Compatability with Existing Systems |
|
|
|
|
|
|
|
|
|
| ||
26 | Design | Compensation Delay Events |
|
|
|
|
|
|
|
|
|
| ||
27 | Design | Compliance with Design Standards/ Codes of Practice |
|
|
|
|
|
|
|
|
|
| ||
28 | Design | Compliance with Good Industry Practice |
|
|
|
|
|
|
|
|
|
| ||
29 | Design | Compliance with Output Specification |
|
|
|
|
|
|
|
|
|
| ||
30 | Design | Compliance with Quality Standards |
|
|
|
|
|
|
|
|
|
| ||
31 | Design | Compliance with Statutory Requirements/Responsibilities |
|
|
|
|
|
|
|
|
|
| ||
32 | Design | Compliance with Third Party Requirements |
|
|
|
|
|
|
|
|
|
| ||
33 | Design | Continuing Development of Design |
|
|
|
|
|
|
|
|
|
| ||
34 | Design | Design Costs |
|
|
|
|
|
|
|
|
|
| ||
35 | Design | Design Delays and Amendments |
|
|
|
|
|
|
|
|
|
| ||
36 | Design | Design Records |
|
|
|
|
|
|
|
|
|
| ||
37 | Design | Design warranties from Sub-Contractors |
|
|
|
|
|
|
|
|
|
| ||
38 | Design | Failure to turn Output Specification in to Design Brief |
|
|
|
|
|
|
|
|
|
| ||
39 | Design | Failure to develop design in required timetable |
|
|
|
|
|
|
|
|
|
| ||
40 | Design | Fitness for purpose (is the design satisfactory to meet operational requirements?) |
|
|
|
|
|
|
|
|
|
| ||
41 | Design | Force Majeure Event |
|
|
|
|
|
|
|
|
|
| ||
42 | Design | Force Majeure Termination |
|
|
|
|
|
|
|
|
|
| ||
43 | Design | Health & Safety Case (including CDM) |
|
|
|
|
|
|
|
|
|
| ||
44 | Design | Legislative/Regulatory Change - Design Requirements |
|
|
|
|
|
|
|
|
|
| ||
45 | Design | Local Authority Omissions or Defaults |
|
|
|
|
|
|
|
|
|
| ||
46 | Design | Local Authority Policy Changes |
|
|
|
|
|
|
|
|
|
| ||
47 | Design | Other Consents & Agreements |
|
|
|
|
|
|
|
|
|
| ||
48 | Design | Planning Approvals/Consents / Permissions |
|
|
|
|
|
|
|
|
|
| ||
49 | Design | Programming of Works |
|
|
|
|
|
|
|
|
|
| ||
50 | Design | Public & Third Party Consultation |
|
|
|
|
|
|
|
|
|
| ||
51 | Design | Redesign/Design Defects |
|
|
|
|
|
|
|
|
|
| ||
52 | Design | Relief Events |
|
|
|
|
|
|
|
|
|
| ||
53 | Design | Testing Design Solution |
|
|
|
|
|
|
|
|
|
| ||
54 | Design | Third party claims |
|
|
|
|
|
|
|
|
|
| ||
55 | Install | Accommodation works for Third Parties |
|
|
|
|
|
|
|
|
|
| ||
56 | Install | Accuracy of Inventory and all Surveys |
|
|
|
|
|
|
|
|
|
| ||
57 | Install | Achievement of Design Standards |
|
|
|
|
|
|
|
|
|
| ||
58 | Install | Archaeological and Historical Finds |
|
|
|
|
|
|
|
|
|
| ||
59 | Install | Capital Costs Overrun |
|
|
|
|
|
|
|
|
|
| ||
60 | Install | Changes requested by Service Provider |
|
|
|
|
|
|
|
|
|
| ||
61 | Install | Changes requested by Local Authority |
|
|
|
|
|
|
|
|
|
| ||
62 | Install | Changes to Output Specification |
|
|
|
|
|
|
|
|
|
| ||
63 | Install | Compensation delay events |
|
|
|
|
|
|
|
|
|
| ||
64 | Install | Compliance with the agreed Investment Programme |
|
|
|
|
|
|
|
|
|
| ||
65 | Install | Compliance with Good Industry Practice/Codes of Practice |
|
|
|
|
|
|
|
|
|
| ||
66 | Install | Compliance with Output Specification |
|
|
|
|
|
|
|
|
|
| ||
67 | Install | Compliance with Quality Standards |
|
|
|
|
|
|
|
|
|
| ||
68 | Install | Compliance with Statutory Requirements/Responsibilities |
|
|
|
|
|
|
|
|
|
| ||
69 | Install | Condition of Underground Supply Network |
|
|
|
|
|
|
|
|
|
| ||
70 | Install | Connection Arrangements (including Delays) |
|
|
|
|
|
|
|
|
|
| ||
71 | Install | Consequences of Early Termination - Service Provider Default |
|
|
|
|
|
|
|
|
|
| ||
72 | Install | Consequences of Early Termination - Local Authority Default |
|
|
|
|
|
|
|
|
|
| ||
73 | Install | Contamination/Hazardous Materials |
|
|
|
|
|
|
|
|
|
| ||
74 | Install | Service Provider default |
|
|
|
|
|
|
|
|
|
| ||
75 | Install | Cost of Alterations |
|
|
|
|
|
|
|
|
|
| ||
76 | Install | Delays caused by Utilities/Statutory Undertakers |
|
|
|
|
|
|
|
|
|
| ||
77 | Install | Disruption |
|
|
|
|
|
|
|
|
|
| ||
78 | Install | Electrical Safety of all Apparatus & Equipment Installed |
|
|
|
|
|
|
|
|
|
| ||
79 | Install | Electrical Testing |
|
|
|
|
|
|
|
|
|
| ||
80 | Install | Emergency Services Liaison |
|
|
|
|
|
|
|
|
|
| ||
81 | Install | Employer's Liability |
|
|
|
|
|
|
|
|
|
| ||
82 | Install | Environmental Liabilities/Damage |
|
|
|
|
|
|
|
|
|
| ||
83 | Install | Failure to Install to Design Standards/Design Brief |
|
|
|
|
|
|
|
|
|
| ||
84 | Install | Fire and Theft |
|
|
|
|
|
|
|
|
|
| ||
85 | Install | Force Majeure Event |
|
|
|
|
|
|
|
|
|
| ||
86 | Install | Force Majeure Termination |
|
|
|
|
|
|
|
|
|
| ||
87 | Install | Fossils and Antiquities |
|
|
|
|
|
|
|
|
|
| ||
88 | Install | Ground Conditions |
|
|
|
|
|
|
|
|
|
| ||
89 | Install | Hazardous Waste |
|
|
|
|
|
|
|
|
|
| ||
90 | Install | Health & Safety (including CDM) |
|
|
|
|
|
|
|
|
|
| ||
91 | Install | Heritage/Conservation Area Works and Compliance |
|
|
|
|
|
|
|
|
|
| ||
92 | Install | Highway Works |
|
|
|
|
|
|
|
|
|
| ||
93 | Install | Implementation Issues to comply with planning legislation |
|
|
|
|
|
|
|
|
|
| ||
94 | Install | Inclement Weather |
|
|
|
|
|
|
|
|
|
| ||
95 | Install | Incorrect cost estimates |
|
|
|
|
|
|
|
|
|
| ||
96 | Install | Incorrect time estimates |
|
|
|
|
|
|
|
|
|
| ||
97 | Install | Industrial Action |
|
|
|
|
|
|
|
|
|
| ||
98 | Install | Intellectual Property |
|
|
|
|
|
|
|
|
|
| ||
99 | Install | Installation Costs |
|
|
|
|
|
|
|
|
|
| ||
100 | Install | Installation Delays |
|
|
|
|
|
|
|
|
|
| ||
101 | Install | Interruption |
|
|
|
|
|
|
|
|
|
| ||
102 | Install | Labour Costs and Availability |
|
|
|
|
|
|
|
|
|
| ||
103 | Install | Labour - Conduct, Claims, Recruitment, Restructuring etc. |
|
|
|
|
|
|
|
|
|
| ||
104 | Install | Latent Defects - Existing Structures and Apparatus |
|
|
|
|
|
|
|
|
|
| ||
105 | Install | Legislative / Regulatory Change - British/EU Standards |
|
|
|
|
|
|
|
|
|
| ||
106 | Install | Legislative / Regulatory Change - Discriminatory |
|
|
|
|
|
|
|
|
|
| ||
107 | Install | Legislative / Regulatory Change - General |
|
|
|
|
|
|
|
|
|
| ||
108 | Install | Legislative / Regulatory Change - Lighting Specific |
|
|
|
|
|
|
|
|
|
| ||
109 | Install | Local Authority Default |
|
|
|
|
|
|
|
|
|
| ||
110 | Install | Material Costs & Supply |
|
|
|
|
|
|
|
|
|
| ||
111 | Install | Peacetime Emergency |
|
|
|
|
|
|
|
|
|
| ||
112 | Install | Planning Approvals/Consents/Permissions/Other Consents |
|
|
|
|
|
|
|
|
|
| ||
113 | Install | Plant & Equipment |
|
|
|
|
|
|
|
|
|
| ||
114 | Install | Project Management & Supervision |
|
|
|
|
|
|
|
|
|
| ||
115 | Install | Protester Action |
|
|
|
|
|
|
|
|
|
| ||
116 | Install | Public Liaison and Consultation |
|
|
|
|
|
|
|
|
|
| ||
117 | Install | Relief Events |
|
|
|
|
|
|
|
|
|
| ||
118 | Install | Rights of Way |
|
|
|
|
|
|
|
|
|
| ||
119 | Install | Service Diversions (including costs and delay) |
|
|
|
|
|
|
|
|
|
| ||
120 | Install | Site Availability and Access |
|
|
|
|
|
|
|
|
|
| ||
121 | Install | Site Preparation |
|
|
|
|
|
|
|
|
|
| ||
122 | Install | Site Safety |
|
|
|
|
|
|
|
|
|
| ||
123 | Install | Site Security |
|
|
|
|
|
|
|
|
|
| ||
124 | Install | Statutory Undertakers/Utilities Works |
|
|
|
|
|
|
|
|
|
| ||
125 | Install | Structural Integrity of Apparatus |
|
|
|
|
|
|
|
|
|
| ||
126 | Install | Sub-Contractor Default |
|
|
|
|
|
|
|
|
|
| ||
127 | Install | Terrorism. War, Insurrection or Invasion |
|
|
|
|
|
|
|
|
|
| ||
128 | Install | Testing |
|
|
|
|
|
|
|
|
|
| ||
129 | Install | Third party claims |
|
|
|
|
|
|
|
|
|
| ||
130 | Install | Third party damage |
|
|
|
|
|
|
|
|
|
| ||
131 | Install | Third Party Liaison, Consultation and Interface |
|
|
|
|
|
|
|
|
|
| ||
132 | Install | Trade Union Liaison |
|
|
|
|
|
|
|
|
|
| ||
133 | Install | Traffic Management |
|
|
|
|
|
|
|
|
|
| ||
134 | Install | Unforeseen ground/site conditions including structures |
|
|
|
|
|
|
|
|
|
| ||
135 | Install | Uninsurable Risks |
|
|
|
|
|
|
|
|
|
| ||
136 | Install | Vandalism |
|
|
|
|
|
|
|
|
|
| ||
137 | Install | Volume Changes - Boundary and/or Classification |
|
|
|
|
|
|
|
|
|
| ||
138 | Install | Waste Management |
|
|
|
|
|
|
|
|
|
| ||
139 | Finance | Availability of Project Finance |
|
|
|
|
|
|
|
|
|
| ||
140 | Finance | Bonds and Warranties |
|
|
|
|
|
|
|
|
|
| ||
141 | Finance | Changes in Government Funding of Local Authorities |
|
|
|
|
|
|
|
|
|
| ||
142 | Finance | Change of Control of SPV/Consortium |
|
|
|
|
|
|
|
|
|
| ||
143 | Finance | Change in Status of Local Authority - LGR etc. |
|
|
|
|
|
|
|
|
|
| ||
144 | Finance | Corrupt Gifts and Payments |
|
|
|
|
|
|
|
|
|
| ||
145 | Finance | Exchange Rate Changes |
|
|
|
|
|
|
|
|
|
| ||
146 | Finance | Failure to deliver Project Finance |
|
|
|
|
|
|
|
|
|
| ||
147 | Finance | Financial Performance of Service Provider / Consortium |
|
|
|
|
|
|
|
|
|
| ||
148 | Finance | Funding for additional works or changes |
|
|
|
|
|
|
|
|
|
| ||
149 | Finance | Income Generation Targets |
|
|
|
|
|
|
|
|
|
| ||
150 | Finance | Inflation |
|
|
|
|
|
|
|
|
|
| ||
151 | Finance | Insurance - Public Liability |
|
|
|
|
|
|
|
|
|
| ||
152 | Finance | Insurance - Others |
|
|
|
|
|
|
|
|
|
| ||
153 | Finance | Interest Rate Changes - before Contract Signature |
|
|
|
|
|
|
|
|
|
| ||
154 | Finance | Interest Rate Changes - post Contract Signature |
|
|
|
|
|
|
|
|
|
| ||
155 | Finance | Market Conditions |
|
|
|
|
|
|
|
|
|
| ||
156 | Finance | Payment for Services |
|
|
|
|
|
|
|
|
|
| ||
157 | Finance | Receipts - Disposal of Assets |
|
|
|
|
|
|
|
|
|
| ||
158 | Finance | Receipts - Third Party Revenues |
|
|
|
|
|
|
|
|
|
| ||
159 | Finance | Refinancing |
|
|
|
|
|
|
|
|
|
| ||
160 | Finance | Revenue/Profit Share above agreed percentages |
|
|
|
|
|
|
|
|
|
| ||
161 | Finance | Residual Value of Apparatus |
|
|
|
|
|
|
|
|
|
| ||
162 | Finance | Service Provider or Consortium Insolvency/Bankruptcy |
|
|
|
|
|
|
|
|
|
| ||
163 | Finance | Sub Contractor Insolvency/Bankruptcy |
|
|
|
|
|
|
|
|
|
| ||
164 | Finance | Sufficiency of Funding to meet Output Specification |
|
|
|
|
|
|
|
|
|
| ||
165 | Finance | Taxation Changes - before Contract Signature |
|
|
|
|
|
|
|
|
|
| ||
166 | Finance | Taxation Changes - post Contract Signature |
|
|
|
|
|
|
|
|
|
| ||
167 | Finance | VAT Changes |
|
|
|
|
|
|
|
|
|
| ||
168 | Comm | Compliance with Output Specification and Contract |
|
|
|
|
|
|
|
|
|
| ||
169 | Comm | Costs of Rectification |
|
|
|
|
|
|
|
|
|
| ||
170 | Comm | Delayed Completion of Connections |
|
|
|
|
|
|
|
|
|
| ||
171 | Comm | Delayed Completion of Installation |
|
|
|
|
|
|
|
|
|
| ||
172 | Comm | Failure of Electricity Supplier |
|
|
|
|
|
|
|
|
|
| ||
173 | Comm | Health & Safety Case |
|
|
|
|
|
|
|
|
|
| ||
174 | Comm | Incorrect time and cost estimates for Commissioning |
|
|
|
|
|
|
|
|
|
| ||
175 | Comm | Licence Award |
|
|
|
|
|
|
|
|
|
| ||
176 | Ops | Accident Damage & Knock-downs |
|
|
|
|
|
|
|
|
|
| ||
177 | Ops | Accuracy of Asset Register/Surveys/Mgt Information System |
|
|
|
|
|
|
|
|
|
| ||
178 | Ops | Adequacy of all Cabling |
|
|
|
|
|
|
|
|
|
| ||
179 | Ops | Adoptions resulting from New Development |
|
|
|
|
|
|
|
|
|
| ||
180 | Ops | Apparatus obsolescence/Availability of Spare Parts |
|
|
|
|
|
|
|
|
|
| ||
181 | Ops | Best Value - Annual Service Report |
|
|
|
|
|
|
|
|
|
| ||
182 | Ops | Best Value - Benchmarking & Market Testing |
|
|
|
|
|
|
|
|
|
| ||
183 | Ops | Best Value - Customer Satisfaction & Consultation |
|
|
|
|
|
|
|
|
|
| ||
184 | Ops | Best Value - BVPP & BVR |
|
|
|
|
|
|
|
|
|
| ||
185 | Ops | Changes in Design Codes of Practice (Operations) |
|
|
|
|
|
|
|
|
|
| ||
186 | Ops | Change in cost of providing the service |
|
|
|
|
|
|
|
|
|
| ||
187 | Ops | Changes in Local Authority Policy |
|
|
|
|
|
|
|
|
|
| ||
188 | Ops | Changes in National Policy |
|
|
|
|
|
|
|
|
|
| ||
189 | Ops | Changes requested by Service Provider |
|
|
|
|
|
|
|
|
|
| ||
190 | Ops | Changes requested by Local Authority |
|
|
|
|
|
|
|
|
|
| ||
191 | Ops | Changes to Inventory |
|
|
|
|
|
|
|
|
|
| ||
192 | Ops | Climate Change Levy |
|
|
|
|
|
|
|
|
|
| ||
193 | Ops | Commercial Viability |
|
|
|
|
|
|
|
|
|
| ||
194 | Ops | Compensation Delay Events |
|
|
|
|
|
|
|
|
|
| ||
195 | Ops | Compliance with Good Industry Practice |
|
|
|
|
|
|
|
|
|
| ||
196 | Ops | Compliance with Quality Standards |
|
|
|
|
|
|
|
|
|
| ||
197 | Ops | Compliance with Statutory Requirements/Responsibilities |
|
|
|
|
|
|
|
|
|
| ||
198 | Ops | Compliance with Output Specification |
|
|
|
|
|
|
|
|
|
| ||
199 | Ops | Consequences of Early Termination - Service Provider Default |
|
|
|
|
|
|
|
|
|
| ||
200 | Ops | Consequences of Early Termination - Local Authority Default |
|
|
|
|
|
|
|
|
|
| ||
201 | Ops | Consequences of Market Testing |
|
|
|
|
|
|
|
|
|
| ||
202 | Ops | Contract Monitoring |
|
|
|
|
|
|
|
|
|
| ||
203 | Ops | Service Provider Default |
|
|
|
|
|
|
|
|
|
| ||
204 | Ops | Service Provider Termination |
|
|
|
|
|
|
|
|
|
| ||
205 | Ops |
|
|
|
|
|
|
|
|
|
| |||
206 | Ops | Depot maintenance |
|
|
|
|
|
|
|
|
|
| ||
207 | Ops | Detection of Outages |
|
|
|
|
|
|
|
|
|
| ||
208 | Ops | Disruption |
|
|
|
|
|
|
|
|
|
| ||
209 | Ops | Electrical Safety of all Apparatus |
|
|
|
|
|
|
|
|
|
| ||
210 | Ops | Electrical Supply and Connections |
|
|
|
|
|
|
|
|
|
| ||
211 | Ops | Electrical, Mechanical and Structural Testing |
|
|
|
|
|
|
|
|
|
| ||
212 | Ops | Emergency Repairs |
|
|
|
|
|
|
|
|
|
| ||
213 | Ops | Employer's Liability |
|
|
|
|
|
|
|
|
|
| ||
214 | Ops | Energy Costs |
|
|
|
|
|
|
|
|
|
| ||
215 | Ops | Energy Management |
|
|
|
|
|
|
|
|
|
| ||
216 | Ops | Energy Supply and Usage |
|
|
|
|
|
|
|
|
|
| ||
217 | Ops | Environmental Liabilities |
|
|
|
|
|
|
|
|
|
| ||
218 | Ops | Failure to meet Performance Standards |
|
|
|
|
|
|
|
|
|
| ||
219 | Ops | Fault Rectification |
|
|
|
|
|
|
|
|
|
| ||
220 | Ops | Fire and Theft |
|
|
|
|
|
|
|
|
|
| ||
221 | Ops | Force Majeure Event |
|
|
|
|
|
|
|
|
|
| ||
222 | Ops | Force Majeure Termination |
|
|
|
|
|
|
|
|
|
| ||
223 | Ops | Health & Safety (including CDM) |
|
|
|
|
|
|
|
|
|
| ||
224 | Ops | Inclement Weather |
|
|
|
|
|
|
|
|
|
| ||
225 | Ops | Industrial Action |
|
|
|
|
|
|
|
|
|
| ||
226 | Ops | Installation of Festive Lighting/Other |
|
|
|
|
|
|
|
|
|
| ||
227 | Ops | Intellectual Property |
|
|
|
|
|
|
|
|
|
| ||
228 | Ops | Inventory & Database Management |
|
|
|
|
|
|
|
|
|
| ||
229 | Ops | Labour Costs and Availability |
|
|
|
|
|
|
|
|
|
| ||
230 | Ops | Labour - Conduct, Claims, Recruitment, Restructuring etc. |
|
|
|
|
|
|
|
|
|
| ||
231 | Ops | Lamp Cleaning and Replacement |
|
|
|
|
|
|
|
|
|
| ||
232 | Ops | Latent Defects - Existing Apparatus |
|
|
|
|
|
|
|
|
|
| ||
233 | Ops | Latent Defects - New Apparatus |
|
|
|
|
|
|
|
|
|
| ||
234 | Ops | Legislative / Regulatory Change - British/EU Standards |
|
|
|
|
|
|
|
|
|
| ||
235 | Ops | Legislative / Regulatory Change - Discriminatory |
|
|
|
|
|
|
|
|
|
| ||
236 | Ops | Legislative / Regulatory Change - General |
|
|
|
|
|
|
|
|
|
| ||
237 | Ops | Legislative / Regulatory Change - Lighting Specific |
|
|
|
|
|
|
|
|
|
| ||
238 | Ops | Liaison with Emergency Services |
|
|
|
|
|
|
|
|
|
| ||
239 | Ops | Lighting Failures |
|
|
|
|
|
|
|
|
|
| ||
240 | Ops | Local Authority Default |
|
|
|
|
|
|
|
|
|
| ||
241 | Ops | Industrial Action |
|
|
|
|
|
|
|
|
|
| ||
242 | Ops | Maintenance & Repair Costs, including Protective Coatings |
|
|
|
|
|
|
|
|
|
| ||
243 | Ops | Management & Supervision of Contract, including Sub-Contractors |
|
|
|
|
|
|
|
|
|
| ||
244 | Ops | Material Costs and Supply |
|
|
|
|
|
|
|
|
|
| ||
245 | Ops | Monitoring Costs |
|
|
|
|
|
|
|
|
|
| ||
246 | Ops | Non-Performance of Apparatus |
|
|
|
|
|
|
|
|
|
| ||
247 | Ops | Operating Costs |
|
|
|
|
|
|
|
|
|
| ||
248 | Ops | Other Damage |
|
|
|
|
|
|
|
|
|
| ||
249 | Ops | Parking Obstructions affecting operations |
|
|
|
|
|
|
|
|
|
| ||
250 | Ops | Permits and Approvals |
|
|
|
|
|
|
|
|
|
| ||
251 | Ops | Pollution |
|
|
|
|
|
|
|
|
|
| ||
252 | Ops | Power Supply failure |
|
|
|
|
|
|
|
|
|
| ||
253 | Ops | Provision of Depot |
|
|
|
|
|
|
|
|
|
| ||
254 | Ops | Provision of Information to Local Authority |
|
|
|
|
|
|
|
|
|
| ||
255 | Ops | Public Liability |
|
|
|
|
|
|
|
|
|
| ||
256 | Ops | Public Liaison and Consultation |
|
|
|
|
|
|
|
|
|
| ||
257 | Ops | Recovery of Third Party Damage Costs |
|
|
|
|
|
|
|
|
|
| ||
258 | Ops | Relief Events |
|
|
|
|
|
|
|
|
|
| ||
259 | Ops | Residual Value of Apparatus |
|
|
|
|
|
|
|
|
|
| ||
260 | Ops | Restrictions on Advertising on Apparatus |
|
|
|
|
|
|
|
|
|
| ||
261 | Ops | Security of Apparatus, Equipment and Vehicles |
|
|
|
|
|
|
|
|
|
| ||
262 | Ops | Service Interfaces/Interfaces with Third Parties |
|
|
|
|
|
|
|
|
|
| ||
263 | Ops | Service not to acceptable levels |
|
|
|
|
|
|
|
|
|
| ||
264 | Ops | Statutory Undertakers/Utilities Works |
|
|
|
|
|
|
|
|
|
| ||
265 | Ops | Step-In by Financiers |
|
|
|
|
|
|
|
|
|
| ||
266 | Ops | Step-In by Local Authority |
|
|
|
|
|
|
|
|
|
| ||
267 | Ops | Storm Damage |
|
|
|
|
|
|
|
|
|
| ||
268 | Ops | Sub- Service Provider Default |
|
|
|
|
|
|
|
|
|
| ||
269 | Ops | Technological Refresh |
|
|
|
|
|
|
|
|
|
| ||
270 | Ops | Technological Obsolescence of Equipment |
|
|
|
|
|
|
|
|
|
| ||
271 | Ops | Termination due to Government Intervention |
|
|
|
|
|
|
|
|
|
| ||
272 | Ops | Terrorism, War, Insurrection or Invasion |
|
|
|
|
|
|
|
|
|
| ||
273 | Ops | Third Party Claims |
|
|
|
|
|
|
|
|
|
| ||
274 | Ops | Third Party Damage |
|
|
|
|
|
|
|
|
|
| ||
275 | Ops | Third Party Liability |
|
|
|
|
|
|
|
|
|
| ||
276 | Ops | Third Party Liaison, Consultation and Interface |
|
|
|
|
|
|
|
|
|
| ||
277 | Ops | Trade Union Liaison |
|
|
|
|
|
|
|
|
|
| ||
278 | Ops | Transfer of Undertakings (TUPE) |
|
|
|
|
|
|
|
|
|
| ||
279 | Ops | Uninsurable Risks |
|
|
|
|
|
|
|
|
|
| ||
280 | Ops | Vandalism |
|
|
|
|
|
|
|
|
|
| ||
281 | Ops | Volume Changes - Boundary and/or Classification |
|
|
|
|
|
|
|
|
|
| ||
282 | Ops | Volume Changes - Energy Consumption |
|
|
|
|
|
|
|
|
|
| ||
283 | Ops | Waste Management |
|
|
|
|
|
|
|
|
|
| ||