4.2 The Authority shall:
[76deliver the Buildings Survey to the Contractor on or before the date of this Agreement];
and
[deliver the Asbestos Survey to the Contractor on or before the date of this Agreement]77.
_________________________________________________________________________________
76 See clause 18.6 (Defects and Asbestos) for the recommended approach to the risk allocation in respect of defects and asbestos. These surveys will only be necessary where buildings are being demolished and/or refurbished. It is anticipated that the surveyor will, depending on the timing of the survey, be engaged by the Authority but will provide a warranty to each of the Contractor, its Building Contractor and the Senior Lenders.
77 In the event that any soil survey or similar is commissioned by the Authority, the Authority will need to ensure that warranties will be available for the Contractor and Sub-Contractors.