10.2 Overall Responsibility
To avoid doubt, the obligations in clause 10.1 are independent obligations. In particular:
(a) the fact that the Contractor has complied with the Stations Requirements but not the Construction Proposals shall not be a defence to an allegation that the Contractor has not satisfied the Construction Proposals provided that the Stations Requirements shall take priority over the Construction Proposals in the event of any discrepancy or inconsistency between them; and
(b) the fact that the Contractor has complied with the Construction Proposals but not the Stations Requirements shall not be a defence to an allegation that the Contractor has not satisfied the Stations Requirements.