22.2  Discrepancies

If an inconsistency or conflict within the Authority's Requirements in relation to the Services becomes apparent to the Contractor, the Contractor shall immediately inform the Authority in writing of that fact and shall obtain the written approval of the Authority to deal with such inconsistency or conflict and after approval by the Authority, the Authority's Requirements shall be amended accordingly and any amendment shall be made without adjustment to the Unitary Charge.  The Authority may not withhold its approval (or impose conditions in giving its approval) where the purpose of such withholding or such conditions is to deal with matters other than the correcting of any such inconsistency or conflict.