58.3  Consequences

In the event that the Contractor has complied with its obligations under clause 58.2 (Relief), then:

58.3.1  the Start on Site Date; and/or

58.3.2  the relevant Planned Services Availability Date and/or following the Planned Services Availability Date, the Longstop Date; and/or

58.3.3  [the relevant Planned Post Completion Works Acceptance Date]

shall be postponed by such time as shall be reasonable for such a Relief Event, taking into account the likely effect of delay; and/or

58.3.4  the Authority shall not be entitled to exercise its right to terminate this Agreement under clause 41.3 (Termination on Contractor Default) and, subject to clause 58.4 (Deductions), shall give such other relief as has been requested by the Contractor.