61.3 Action by Authority
61.3.1 Following service of such notice, the Authority shall take such action as notified under clause 61.2 (Notice to the Contractor) and any consequential additional action as it reasonably believes is necessary (together, the "Required Action") and the Contractor shall give all reasonable assistance to the Authority while it is taking the Required Action.
61.3.2 Where the Required Action has been taken otherwise than as a result of a breach by the Contractor the Authority shall undertake the Required Action in accordance with Good Industry Practice and shall indemnify the Contractor against all Direct Losses where it fails to do so.