9.3  Road Closure Schedule

The Road Closure Schedule for the first Payment Year is set out in Schedule 8 (Road Closure Schedule).  The Service Provider shall submit to the Authority Representative in accordance with the Review Procedure a proposed Road Closure Schedule in respect of the Project Network including details of the proposed start and end dates for each period of Road Section Closure and the works to be carried out not later than 1st January in each Payment Year after the First Payment Year, for the next succeeding Payment Year.