9.4 Revision of Road Closure Schedule
Not later than thirty (30) Business Days prior to the commencement of any Quarter, the Service Provider may submit to the Authority Representative, in accordance with the Review Procedure, a revision of the current Road Closure Schedule showing proposed revisions to the periods of Road Section Closure in respect of such Quarter. If there is no objection to any such revision pursuant to the Review Procedure, then it shall replace the Road Closure Schedule in respect of such Quarter.