9.6  Authority Rescheduling of Road Section Closures

The Authority Representative may, upon sixty (60) Business Days prior written notice, require the Service Provider to re-schedule a period of Road Section Closure set out in a Road Closure Schedule, provided that the Authority Representative may not require:

(a)  that such period of Road Section Closure be brought forward by more than sixty (60) days from the scheduled date of commencement of such period of Road Section Closure; or

(b)  that a period of Road Section Closure be deferred by more than sixty (60) days from the scheduled date of commencement of such period of Road Section Closure.