13.1  Core Investment Programme

Irrespective of any provision to the contrary in the Core Investment Programme, the Service Provider shall complete each Milestone specified in column 3 of Table 1 by the Milestone Completion Date (Projected) stated opposite in column 2 of Table 1.

Table 1

Milestone Number

Milestone Completion Date (Projected)

Milestone7

1

6 Months after the Service Commencement Date

 

2

12 Months after the Service Commencement Date

 

3

18 Months after the Service Commencement Date

 

4

24 Months after the Service Commencement Date

 

5

30 Months after the Service Commencement Date

 

6

36 Months after the Service Commencement Date

 

7

42 Months after the Service Commencement Date

 

8

48 Months after the Service Commencement Date

 

9

54 Months after the Service Commencement Date

 

10

60 Months after the Service Commencement Date

 




__________________________________________________________________________________________________

7  Milestones to be defined and reviewed to ensure consistency with the payment mechanism.