13.3  Failure to complete Milestones on time

If the Service Provider fails to achieve completion of a Milestone by the relevant Milestone Completion Date (Projected):

(a)  a Milestone Default Termination Point shall accrue on that and each subsequent Milestone Completion Date (Projected) until the Service Provider achieves completion of the relevant Milestone;

(b)  to the extent that a Service Provider failed to achieve a Milestone by the relevant Milestone Completion Date (Projected) but subsequently achieves completion of that Milestone, any Milestone Default Termination Points accrued in respect of that Milestone shall be immediately cancelled and shall not apply for the purposes of clause 62.3 (Service Provider Default);

(c)  if the Service Provider fails to achieve completion of Milestone 10 on the relevant Milestone Completion Date (Projected), a Milestone Default Termination Point shall accrue.  If Milestone 10 remains uncompleted a further Milestone Default Termination Point shall accrue in respect of each period of one hundred and eighty (180) days in which Milestone 10 remains uncompleted.