PART C - CORE INVESTMENT PERIOD AND CERTIFICATION
>
14 Certification of Milestones and Subsequent Works
14
Certification of Milestones and Subsequent Works
More Information
14.1 Certification of Milestone Completion
14.2 Rectification of Snagging Items
14.3 Failure to complete Snagging
14.4 Certification following completion of the Core Investment Programme
14.5 Notification by the Service Provider to the Authority
14.6 Inspections
14.7 Written confirmation
14.8 Non-Compliance
14.9 Rectification
14.10 Disagreement with Authority notice
14.11 Delay to Completion
14.12 Certificate of Compliance
14.13 Rectification of Snagging Items
14.14 Failure to Complete Snagging
14.15 Inclusion in MIS
14.16 No effect on Service Provider's Obligations