20.4 Failure to Obtain Consent
From the date twenty (20) Business Days after the date the Authority first meets with the Service Provider pursuant to clause 20.3(b) until the earlier of:
(a) the Service Provider or the Authority obtains the Necessary Consent to affix the Apparatus;
(b) the Apparatus is installed in another location in accordance with [paragraphs 5.5(h) or 5.9(f) of the Output Specification;]
(c) a Design Variation Approval is issued pursuant to paragraph 8 of the Review Procedure;
(d) the relevant Apparatus is De-Accrued in accordance with Schedule 14 (Accrual and De-Accrual Process);
(e) an Authority Change is implemented in accordance with the Change Protocol,
any failure to obtain a Necessary Consent to affix Apparatus to a structure other than other Apparatus shall constitute an Excusing Cause and the provisions of clause 40 (Excusing Causes) shall apply.