62.5 Termination Notice
The Termination Notice shall specify:
(a) the type and nature of the Service Provider Default that has occurred, giving reasonable details;
(b) in the case of any Service Provider Default referred to in clause 62.3(a) (Material Breach), clause 62.3(g) (Assignment and Subcontracting), clause 62.3(h) (Change of Control), or clause 62.3(o) (Insurance) that this Contract shall terminate on the day falling forty (40) Business Days after the date that the Service Provider receives the Termination Notice, unless:
(i) in the case of a Service Provider Default referred to in clause 62.3(a) (Material Breach), the Service Provider puts forward an acceptable rectification programme within twenty (20) Business Days after the date the Service Provider receives the Termination Notice (and implements such programme in accordance with its terms and rectifies the Service Provider Default in accordance with the programme; or
(ii) in the case of a Service Provider Default referred to in clause 62.3(a) (Material Breach), clause 62.3(g) (Assignment and Subcontracting), clause 62.3(h) (Change of Control), or clause 62.3(o) (Insurance), the Service Provider rectifies the Service Provider Default within forty (40) Business Days after the date the Service Provider receives the Termination Notice; or
(c) in the case of any other Service Provider Defaults (not being a Service Provider Default referred to in clause 62.5(b)) this Contract shall terminate on the date falling twenty (20) Business Days after the Service Provider receives the Termination Notice.