66.8 Cessation of a Force Majeure Event
The Affected Party shall notify the other party as soon as practicable after the Force Majeure Event ceases or no longer causes the Affected Party to be unable to comply with its obligations under this Contract. Following such notification the Contract shall continue to be performed on the terms existing immediately prior to the occurrence of the Force Majeure Event.