TABLE 1.1 - SUMMARY OF MILESTONE TARGETS
Performance Standard at the end of CIP | ||||||||||
1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | |||
Strategic Route and [Main Distributor Network] (NCImain) | 18.6 | |||||||||
NCI | Secondary Distributor Network (NCIsec) | 9.9 | ||||||||
Link Road Network (NCIlink) | 9.9 | |||||||||
[Local Access Road Network] (NCIlocal) | 9.9 | |||||||||
[Prestige], [Primary and Secondary Footway Network] (FCIprest) | 6.6 | |||||||||
Link and Local Access Walking and Cycling Routes Network (FCIlink) | 6.6 | |||||||||
>2.4 | ||||||||||
Structures and bridges | 100% compliance with target 1.8 in Table 1.2 | |||||||||
tunnels | All requirements in targets 1.9.1 to 1.9.6 in Table 1.2 are satisfied. | |||||||||
All Pumping Stations are upgraded in accordance with the requirements set out in the relevant Asset Survey Report | ||||||||||
No more than [ ] years old | ||||||||||
[Street Lighting] | 100% compliance with targets 1.10.1 to 1.10.8 in Table 1.2 | |||||||||