5.10  Planned Inspection and Testing, Lighting Performance Inspection and Testing

(a)  The Service Provider shall ensure that all Deemed to Comply Apparatus is subjected to a full lighting performance inspection and test within six (6) Months of the Service Commencement Date. Thereafter, the Service Provider shall carry out a planned inspection and test regime that ensures, subject to implementation of the correct maintenance regime as recommended by manufacturers, that all Apparatus continues to perform in accordance with the equipment specification levels. In order that lighting performance can be certified by the Service Provider as compliant with this PS2 the Service Provider shall ensure that:

(i)  the optical system and enclosure is not degraded, damaged or soiled and is sealed to the manufacturers recommendations;

(ii)  the optical setting of the Luminaire is as recorded in the MIS;

(iii)  the Luminaire body is intact and sealed in accordance with the manufacturers recommendations;

(iv)  the Luminaires are securely attached to Apparatus and are correctly aligned;

(v)  the Luminaires are not obstructed by foliage.

(b)  The Service Provider shall ensure that all Apparatus replaced as part of an Investment Programme or Accrued are subject to planned photometric efficiency testing regime that complies fully with the requirements of PS5 and the relevant PS2 Method Statement.