5.15  Performance Monitoring

(a)  PS2 Performance Target A: the Service Provider shall carry out an Outage Detection Cycle in accordance with the relevant PS2 Method Statement:

(i)  each Lighting Point is inspected to identify the number of Lighting Points which are In Light and operating correctly;

(ii)  all Apparatus is inspected to identify any other visual defect or Fault.

(b)  PS2 Performance Target B: in order that the Service Provider can demonstrate that Lighting Points are providing lights In Light compliant with the Specific Lighting Design Standard in any Month the Authority shall be entitled to require the Service Provider to carry out photometric tests in accordance with PS2 Method Statements (Planned Maintenance, Inspection and Testing).

(c)  PS2 Performance Target C: the Service Provider shall put in place and operate a planned maintenance, test and inspection regime compliant with the frequencies set out in Table 2.