PS2 Performance Target C
2.4 Failure to comply with the requirements of PS2 Performance Target C in relation to all Apparatus as identified in Table 2 in paragraph 11.1(c) of the Output Specification as items 3, 4 and 5 shall lead to an Adjustment to the Monthly Payment in accordance with the following formula:
= | Number of Failures x X + Y | |
Where: | ||
Number of Failures | = | the number of relevant units of Apparatus which have not been either cleaned, painted and/or maintained at the times specified in items 3, 4 and 5 in Table 2 in paragraph 11.1(c) of the Output Specification; |
X | = | £25 (Indexed) for the first day of the Month following the Month during which the relevant failure arose; |
Y | = | in relation to items 3, 4 and 5 in Table 2 in paragraph 11.1(c) of the Output Specification £1 for each day thereafter. |
2.5 Failure to comply with the requirements of PS2 Performance Standard C in relation to Apparatus specified as items 1, 2, 6 and 7 in Table 2 in paragraph 11.1 of the Output Specification shall lead to an Adjustment to the Monthly Payment in accordance with the following formula:
= | Number of Failures x X | |
Where: | ||
Number of Failures | = | the number of relevant units of Apparatus which have not been either inspected and/or tested in accordance with the Relevant Standards set out in PS2 of the Output Specification at the times specified in items 1, 2, 6 and 7 in Table 2 in paragraph 11.1(c) of the Output Specification; |
X | = | £25 (Indexed). |