7  Implementation of a Change by the Authority

7.1  The Authority may implement any Change itself pursuant to paragraph 4.5 (Implementation) of Part 2 (Low Value Changes), or paragraph 2.10 (Contractor Response) of Part 3 (Medium Value Changes) or paragraph 7.4 (Authority Stage 2 Confirmation) of Part 4 (High Value Changes) provided that where the Change is an Alteration it may only be implemented by the Authority:

(a)  if it comprises the provision of separate facilities at the relevant Facility and does not require any Alteration to any existing buildings or other facilities (other than any Alterations comprising connection into utilities or other service media at the relevant Facility necessary to implement the relevant Change); or

(b)  the Authority shall undertake the Change in accordance with Good Industry Practice and shall pay to the Contractor any Direct Losses incurred by the Contractor as a result of a failure to do so.