SECTION J
SECTION | RATE ITEM | BRIEF DESCRIPTION | UNIT |
| ||||||||
J |
| ABANDONED/TRIAL HOLES |
|
|
|
| ||||||
|
|
|
|
|
|
| |||||||
1 | EXCAVATE, BACK FILL AND PERMANENTLY RE-INSTATE TRIAL HOLE FOR COLUMN AND POST UP TO AND INCLUDING 8M | No. |
|
|
| |||||||
2 | EXCAVATE, BACK FILL AND PERMANENTLY RE-INSTATE TRIAL HOLE FOR COLUMN AND POST OVER 8M AND UP TO AND INCLUDING 12M. | No. |
|
|
| |||||||
3 | EXCAVATE, BACK FILL AND TEMPORARILY RE-INSTATE TRIAL HOLE FOR COLUMN AND POST UP TO AND INCLUDING 8M | No. |
|
|
| |||||||
4 | EXCAVATE, BACK FILL AND TEMPORARILY RE-INSTATE TRIAL HOLE FOR COLUMN AND POST OVER 8M AND UP TO AND INCLUDING 12M. | No. |
|
|
| |||||||
5 | EXCAVATE HOLE FOR COLUMN OR POST UP TO AND INCLUDING 1M DEEP, ABANDON EXCAVATION, BACK FILL AND PERMANENTLY RE-INSTATE. | No. |
|
|
| |||||||
6 | EXCAVATE HOLE FOR COLUMN OR POST OVER 1M DEEP UP TO AND INCLUDING 1.5M DEEP, ABANDON EXCAVATION, BACK FILL AND PERMANENTLY RE-INSTATE. | No. |
|
|
| |||||||