3.3 Design and Construct

For a design and construct contract, the government prepares a design brief which outlines the functional and key user requirements (in performance terms) for the works but is less fully developed than the design documentation required for a construct-only contract. The government then seeks tenders for completion of the detailed design, consistent with the design brief and construction of the works described in the design brief.

The following figure illustrates the contractual relationships in a design and construct contract i.e. the principal enters into a single contract with the construction contractor who is required to provide design expertise.

Figure 5: Design and Construct Structure

The following table lists features of the design and construct model -

Advantages

Disadvantages (and issues that may need managing)

Single point of accountability for design and construction

Administrative efficiency

Fast track - time saving because construction can commence ahead of full design documentation (provided there is adequate control over design quality)

Contractor has the opportunity to contribute construction experience into the design, resulting in innovation and efficiencies

Contractor normally warrants design including 'fitness for purpose'

Lump sum for design and construction

Limited input by contractor into early design

Longer tender period needed to allow tenderers to assess design risk

Principal may pay a premium to transfer design risks

Lack of focus on lifecycle costs and considerations

Government retains whole-of-life asset risk

Government may be liable for time and cost overruns

More Information