11.1.2  Genuine pre-estimate

The rate of liquidated damages payable in any project must be a genuine pre-estimate of the costs and losses government is likely to incur from the delay in service delivery. Otherwise the amount may be judged to constitute a penalty and will not be enforceable. Liquidated damages may be reduced where the private party provides adequate temporary arrangements (e.g. temporary accommodation in the case of an accommodation project).