17.2.3 Recovery of costs and losses
Provided that the private party has complied with its obligations for claiming Compensation, where the occurrence of a Compensation Event:
(a) means that:
(i) during the design and construction phase, the private party is entitled to an extension of time in accordance with Chapter 16 (Relief Events); or
(ii) during the operating term, the ability of the private party to perform any of its obligations under the project agreement is adversely affected; and
(b) causes the private party to incur additional costs or loses revenue,
then the private party will be entitled to claim Compensation in accordance with the Compensation Principles.