21.2.4 Mitigation
During the period for which the private party is granted relief, it must still use all reasonable endeavours to prevent or mitigate the effects of the Force Majeure Event and must take all steps in accordance with Good Industry Practice to overcome or minimise the consequence of the Force Majeure Event.