25.3 Voluntary Termination
In addition to Default Termination Events and Force Majeure Termination Events, government may at any time, in its sole discretion and without giving any reasons, terminate the project agreement by giving a specified period of notice ("Voluntary Termination"). Where government has directed the private party not to reinstate or repair damage114, and the relevant damage was not caused by a Force Majeure Event or private party default, termination of the project agreement by government will be treated as a Voluntary Termination.
___________________________________________________________________________________________________
114 See section 22.2 of Chapter 22 (Reinstatement and repair).