26. Termination Payments
| Principle On early termination of the project agreement, government generally pays a Termination Payment to the private party. This payment is calculated in accordance with the principles set out in this Chapter. |
This Chapter assumes that the private party has not taken residual risk on the project assets, and that those assets are transferred to government upon termination. In other circumstances, different termination payments may be appropriate.