14.1.4 Raw PSC results (non-risk-adjusted)
Table 14-1 shows the Raw PSC split into construction cost and operating costs (NPC basis).
Table 14-1: Raw PSC - Construction and operating costs (net present cost)
| Cost item | NPC | |
| Direct construction costs |
| |
| Project design | 0.5 |
|
| Land acquisition and development | 5.0 |
|
| D&C contract price (incl. car park) | 139.6 |
|
| Payments to consultants | 1.0 |
|
| Plant and equipment | 46.5 |
|
| Capital improvement (incl. car park) | 11.8 |
|
| Refurbishment cost | 27.3 |
|
| Indirect construction cost |
| |
| Overheads | 2.9 |
|
| Total construction costs | 234.6 |
|
| Direct operating costs |
| |
| Hospital maintenance costs | 30.0 |
|
| Cost of materials | 10.5 |
|
| Wages and salaries | 37.5 |
|
| Other employee costs | 7.5 |
|
| Electricity etc. | 14.0 |
|
| Direct management costs | 7.0 |
|
| Insurance | 8.8 |
|
| Indirect operating costs |
| |
| Operating overheads | 1.4 |
|
| Administration overheads | 3.8 |
|
| Indirect capital cost allocation | 0.7 |
|
| Less third-party revenue | (35.0) |
|
| Total operating costs | 86.2 |
|
| Total Raw PSC (excl. GST) | 320.8 |
|
Cost items in Table 14-1 are in NPC terms and will differ from numbers in Section 14.1.2. For example, the capital cost, $150m nominal (referred to in Section 14.1.2) corresponds to $139.6m in NPC terms.