Allocation | Code | Risk | Timing | Description | Consequence | Risk Expert | Applied to | Base | Scenario | Consequence | Probability | Value |
Retained | O5 | Maintenance Risk: Patient Area | Risk that maintenance costs differ from expectations | Increase in costs | [Risk Expert/Source of Risk Estimates for each risk] | 20% of the cost of maintenance and materials | (1,000) | |||||
Below base amount | -5% | 5% | 3 | |||||||||
No deviation from base | 0% | 15% | 0 | |||||||||
Overrun: likely | 45% | 45% | (223) | |||||||||
Overrun: moderate | 75% | 25% | (206) | |||||||||
Overrun: extreme | 120% | 10% | (132) | |||||||||
Subtotal | 100% | (558) | ||||||||||
L1 | Regulatory Risk | Risk that a change in law has an adverse effect on the Project | Increase in cost | - | (1,000) | |||||||
Change in Law Risk | 100% | 100% | (1,000) |